Control Account
A control account is a management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.
Know it well enough for the exam? Questions on Control Account are scenario-based, not definitional.
Practice it freeExplanation
A control account is a point in the WBS, typically above the work package level, where the project integrates scope, schedule, and cost data for earned value management (EVM). It serves as the intersection of the WBS and the organizational breakdown structure (OBS), linking a defined body of work to a single responsible manager or organizational unit.
Each control account includes one or more work packages and possibly planning packages (for work not yet decomposed). It has its own budget, schedule, and assigned responsibility, allowing the project manager to track earned value performance at a meaningful management level without needing to measure every individual work package separately.
Control accounts are essential for large projects using earned value management. They provide the structure needed to aggregate performance data, identify variances, and take corrective action at the right organizational level. The sum of all control account budgets equals the performance measurement baseline.
Key Points
- •Management control point for integrating scope, budget, and schedule
- •Intersection of the WBS and organizational breakdown structure
- •Contains work packages and possibly planning packages
- •Used for earned value performance measurement
Exam Tip
Control accounts are where EVM performance measurement happens. Each control account is assigned to a single manager and integrates scope, schedule, and cost data.
Frequently Asked Questions
Related Topics
Work Package
A work package is the lowest level of the work breakdown structure, representing a deliverable or project work component that can be estimated, scheduled, monitored, and controlled.
Planning Package
A planning package is a WBS component below the control account with known work content but without detailed schedule activities, used as a placeholder for future planning.
Work Breakdown Structure (WBS)
A work breakdown structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
Scope Baseline
The scope baseline is the approved version of the project scope statement, work breakdown structure (WBS), and its associated WBS dictionary, used as a reference for measuring project scope performance.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Scope Management
Practice Control Account
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.