Skip to content
PMPCAPM

Continuing Certification Requirements

The Continuing Certification Requirements (CCR) program is PMI’s framework that defines how credential holders maintain their certifications through ongoing professional development and renewal fees.

Share:

Know it well enough for the exam? Questions on Continuing Certification Requirements are scenario-based, not definitional.

Practice it free

Explanation

The CCR program ensures that PMI credential holders remain current in their knowledge and skills throughout their careers. The program establishes the cycle length, PDU requirements, and renewal process for each certification. For PMP holders, the cycle is three years with a 60-PDU requirement. For CAPM holders, the cycle is three years with a 15-PDU requirement. A renewal fee must also be paid at the end of each cycle.

The CCR program uses the CCRS (Continuing Certification Requirements System), an online platform where credential holders report PDUs, track their progress, and complete their renewal. PMI conducts random audits to verify that reported PDUs represent legitimate professional development activities. Practitioners must maintain records that support their claimed PDUs.

Understanding the CCR program is part of professional responsibility. Falsely reporting PDUs or failing to maintain your credential while still representing yourself as certified are violations of the PMI Code of Ethics. The exam may include questions about the CCR program as part of broader professional responsibility scenarios.

Key Points

  • •Defines cycle length, PDU requirements, and renewal process for each credential
  • •PMP: 3-year cycle, 60 PDUs, plus renewal fee
  • •CAPM: 3-year cycle, 15 PDUs, plus renewal fee
  • •Random audits verify legitimacy of reported PDUs

Exam Tip

Know the specific cycle lengths and PDU requirements for PMP and CAPM. Also remember that falsely claiming PDUs is an ethical violation, not just an administrative one.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Ethics & Professional Responsibility

Study full domain →

Practice Continuing Certification Requirements

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.