CAPM Practice: Validate requirements through product delivery
Question 56 of 68 in Validate requirements through product delivery
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Comparing expected outcomes (defined in requirements as hypotheses) with actual measured outcomes after delivery to determine whether the solution achieved its intended purpose
Explanation
Requirements defined as hypotheses (if we build X, user behavior Y will change by Z%) enable post-delivery validation: measure actual outcomes against the hypothesis. This evidence-based approach produces definitive answers about whether requirements were correctly specified and whether the solution delivered value.
**Why not A:** Statistical hypothesis testing is a mathematical technique for analyzing data distributions, not the same as hypothesis testing in post-delivery validation. Requirements-based hypothesis testing compares expected business outcomes with actual measured results to assess whether the solution achieved its purpose.
**Why not C:** Hypothesis testing in requirements validation is applicable to all product delivery, not just research projects. Any feature can be framed as a hypothesis (if we build X, outcome Y will change by Z%), making it a broadly useful validation approach for commercial products and internal tools alike.
**Why not D:** Testing stakeholder hypotheses about users before delivery is part of discovery and elicitation, not post-delivery validation. Post-delivery hypothesis testing specifically measures actual outcomes after the solution is deployed to determine whether it achieved the intended results.
Key Concept
This question covers Validate requirements through product delivery under Validate requirements through product delivery (Business Analysis Frameworks).