CAPM Practice: Validate requirements through product delivery
Question 55 of 68 in Validate requirements through product delivery
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The high-level conditions the complete product must satisfy before the project is considered successful — defined early and used to evaluate overall delivery at project completion
Explanation
Project-level acceptance criteria define what 'done' means for the entire project: the business outcomes, performance levels, and quality standards the whole product must achieve. Individual story acceptance criteria validate pieces; project acceptance criteria validate the whole.
**Why not A:** "Criteria used to select which product to build" confuses acceptance criteria with product selection or portfolio management decisions. Product acceptance criteria define the conditions that a delivered product must satisfy to be accepted by the customer or stakeholders. They do not determine which product concept to pursue in the first place.
**Why not C:** "Minimum feature count required for release" conflates acceptance criteria with a minimum viable product (MVP) concept. Product acceptance criteria are specific, measurable conditions the complete product must satisfy, not a numerical threshold of features. A product could meet all acceptance criteria with fewer features if the whole product satisfies its defined conditions.
**Why not D:** "Regulatory approval criteria" narrows acceptance criteria to only compliance-related conditions. While regulatory requirements may be part of acceptance criteria, product acceptance criteria encompass a much broader set of conditions including functional correctness, performance, usability, and stakeholder satisfaction—not just regulatory compliance.
Key Concept
This question covers Validate requirements through product delivery under Validate requirements through product delivery (Business Analysis Frameworks).