CAPM Practice: Validate requirements through product delivery
Question 57 of 68 in Validate requirements through product delivery
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: When a previously valid requirement becomes obsolete due to business changes, technology evolution, or delivery of a better solution — the requirement should be formally retired from the active backlog to prevent unnecessary work
Explanation
Requirements retire when business conditions change, making them irrelevant. A market shift, regulatory change, or better solution may make a previously prioritized requirement unnecessary. Formally retiring obsolete requirements prevents teams from building things that are no longer needed.
**Why not A:** Removing poorly written requirements from the backlog is requirements cleanup or grooming, not retirement. Requirements retirement specifically refers to formally retiring previously valid requirements that have become obsolete due to changing business conditions, technology, or better solutions.
**Why not C:** A scheduled archival at project close is project documentation archiving, not requirements retirement. Requirements retirement can happen at any point during the project lifecycle when business conditions change, not only at project closure.
**Why not D:** When business analysts retire and transfer knowledge, that is personnel succession planning, not requirements retirement. Requirements retirement is about the lifecycle of individual requirements becoming obsolete, not about BA staff transitions.
Key Concept
This question covers Validate requirements through product delivery under Validate requirements through product delivery (Business Analysis Frameworks).