CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 30 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Active and ongoing throughout the project to provide feedback and set priorities
Explanation
Adaptive approaches require active, ongoing stakeholder involvement — especially the product owner or customer representative. Sprint reviews require stakeholder attendance for feedback. Backlog refinement sessions involve stakeholders in clarifying requirements. This continuous engagement is a feature, not a burden — it's the mechanism by which the product stays aligned with real needs throughout development.
**Why not A:** While product metrics are valuable, they cannot replace human stakeholder judgment on priorities, business context, and strategic direction. Metrics inform decisions but do not make them — stakeholders provide the business perspective that data alone cannot capture.
**Why not B:** Limiting stakeholder involvement to initiation and closure would deprive the project of ongoing feedback, priority adjustments, and course corrections. This is a predictive mindset where requirements are fixed upfront, which contradicts adaptive principles.
**Why not D:** Minimizing stakeholder involvement to reduce scope change actually increases risk — without regular feedback, the team may build the wrong product. Adaptive approaches view scope changes driven by stakeholder feedback as valuable course corrections, not threats.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).