CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 29 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Develop a methodology selection framework where software/uncertain projects use adaptive, infrastructure uses predictive, and process improvements use hybrid or adaptive depending on novelty
Explanation
A portfolio-level approach requires matching methodology to project characteristics. Mandating one approach for all projects ignores the different needs of different project types. A methodology selection framework that guides teams to appropriate methods — with appropriate governance for each — allows the organization to be both agile (where needed) and rigorous (where needed) without imposing unnecessary constraints.
**Why not A:** Mandating predictive methodology for all projects ignores that 60% of the portfolio is software development with uncertain requirements. A predictive approach suits the infrastructure projects with detailed specs, but forcing it onto uncertain work leads to rework and late discovery of changing needs.
**Why not B:** Mandating agile Scrum for all projects ignores that 30% of the portfolio is infrastructure construction with detailed specifications, where a predictive approach is typically better suited. A one-size-fits-all mandate imposes unnecessary constraints regardless of which approach is chosen.
**Why not D:** Letting each team select its own methodology with no organizational guidance leads to inconsistency and governance gaps across the portfolio. Teams benefit from a framework that guides them to appropriate methods based on project characteristics rather than having no guidance at all.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).