Skip to content
CAPMMedium

CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 31 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

A project team working on an adaptive project is told by management that no requirements can change once the sprint begins. This directive:
Show answer & explanation

Correct answer: Conflicts with the fundamental adaptive principle of responding to change, though sprint-level stability is normal

Explanation

Sprint-level stability (not changing the sprint goal or sprint backlog during an active sprint) IS an adaptive best practice — it protects the team's focus. But management saying 'no requirements can change ever' misunderstands adaptive principles. Between sprints, requirements CAN and SHOULD change based on feedback. The sprint provides a short window of stability while the overall product direction remains adaptable.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free