Skip to content
CAPMMedium

CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 17 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

A project manager is explaining adaptive approaches to a skeptical executive. The executive asks 'How can we plan costs without knowing requirements?' The BEST response is:
Show answer & explanation

Correct answer: Adaptive projects use relative sizing and velocity-based forecasting to estimate cost within a budget envelope, with the product owner making prioritization decisions when the budget is reached

Explanation

Adaptive project cost management uses time-box and budget-envelope approaches: fix the time and cost, let scope flex. Teams estimate work using relative sizing (story points), measure velocity (how much they complete per iteration), and forecast how much can be delivered within the budget. The product owner decides which backlog items to prioritize — ensuring the most valuable work is delivered first. When budget is reached, the product has the highest-value features.

**Why not A:** While fixing cost and flexing scope is part of adaptive cost management, this answer is too narrow. It only addresses one dimension (scope flexibility) without mentioning relative sizing, velocity-based forecasting, or the product owner's role in prioritization — all essential elements of how adaptive projects manage costs.

**Why not B:** A detailed upfront bottom-up estimate of the entire backlog assumes requirements are known and stable, which is exactly what the executive is questioning. Baselining and controlling against it is a predictive technique; adaptive approaches instead forecast within a budget envelope using velocity and let the product owner reprioritize as learning occurs.

**Why not C:** Claiming that adaptive projects cannot plan costs is factually incorrect and would undermine executive confidence. Adaptive approaches do plan costs effectively through time-boxed budgets, velocity forecasting, and incremental funding — they simply approach it differently than predictive methods.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free