CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 16 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Observation, experience, and what has been proven through actual work
Explanation
Empiricism is the principle that knowledge comes from experience and direct observation. In adaptive project management, teams make decisions based on what they observe in actual working increments, actual user feedback, and actual process performance — rather than theoretical plans or assumptions. This is why frequent inspection is essential: it creates the empirical evidence that drives decisions.
**Why not B:** Expert opinions and historical project data can inform estimates, but they are not empirical evidence from the current work. Empiricism relies on what the team actually observes in its own increments, feedback, and process performance rather than on judgment or data carried over from other projects.
**Why not C:** Established industry standards and best practices are predetermined guidance, not evidence gathered from the actual work. Empiricism favors inspecting real results and adapting accordingly rather than following prescribed approaches regardless of what is observed.
**Why not D:** Mathematical models and probability calculations are predictive tools built on assumptions. Empiricism emphasizes decisions grounded in observed outcomes from actual work rather than theoretical forecasts.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).