CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 16 of 61 in Explain when it is appropriate to use an adaptive approach
Show answer & explanation
Correct answer: Observation, experience, and what has been proven through actual work
Explanation
Empiricism is the principle that knowledge comes from experience and direct observation. In adaptive project management, teams make decisions based on what they observe in actual working increments, actual user feedback, and actual process performance — rather than theoretical plans or assumptions. This is why frequent inspection is essential: it creates the empirical evidence that drives decisions.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).