CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 18 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Comprehensive upfront planning that eliminates uncertainty
Explanation
Adaptive approaches do NOT provide comprehensive upfront planning that eliminates uncertainty — that is a characteristic of predictive approaches. Adaptive approaches embrace uncertainty and manage it through iteration. The benefits of adaptive approaches include early value delivery, change incorporation, and risk reduction through feedback — all of which stem from accepting, not eliminating, uncertainty.
**Why not A:** Early delivery of value is a genuine benefit of adaptive approaches. Work is delivered incrementally, so customers receive usable outcomes before the entire project is complete.
**Why not C:** Regular feedback loops are a core benefit of adaptive approaches. Frequent reviews let the team validate direction early and reduce the risk of building the wrong product.
**Why not D:** Incorporating changing requirements is a defining benefit of adaptive approaches. The backlog is continuously refined and reprioritized, so change can be absorbed between iterations.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).