CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 42 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Kanban — because the continuous flow of unpredictable, varying-priority tickets fits a pull-based flow system better than fixed-length sprints
Explanation
Support/maintenance work with continuous, varying-priority incoming requests fits Kanban's continuous-flow model better than Scrum's sprint model. Kanban allows the team to pull new work when capacity exists, prioritize by urgency, and respond to new tickets immediately — without waiting for the next sprint planning. WIP limits prevent overload while allowing flexible prioritization.
**Why not A:** Shortening sprints to one week does not change the underlying mismatch. Work is still committed at sprint planning, so urgent tickets arriving mid-sprint must either wait or disrupt the sprint goal, and the shorter cadence adds more ceremony overhead without addressing the unpredictable arrival of tickets.
**Why not C:** Support tickets arrive unpredictably and with varying priority, so they cannot be planned in advance. A predictive approach assumes stable, knowable work up front, which contradicts the nature of maintenance and support work described in the scenario.
**Why not D:** Sprints do provide structure, but that structure comes from fixed-length timeboxes and sprint commitments that fit poorly with a continuous stream of unpredictable tickets. Structure for flow-based work is better provided by Kanban's visual board, WIP limits, and explicit policies.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).