CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 41 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: To inspect the increment and adapt the product backlog based on stakeholder feedback
Explanation
The sprint review's primary purpose is inspection and adaptation: the team demonstrates what was built, stakeholders provide feedback, and the product owner uses that feedback to adjust the product backlog. It is a collaborative working session, not a status report. The backlog may be re-prioritized, items added or removed, and direction adjusted based on the review.
**Why not B:** Planning the activities for the next sprint happens in sprint planning, not the sprint review. While feedback gathered in the review may influence what is selected next, the review itself focuses on inspecting the increment and adapting the product backlog.
**Why not C:** The sprint review is not a performance evaluation forum, and evaluating individual team members is not the Scrum Master's role. The review centers on the product increment and stakeholder feedback, not on assessing individuals.
**Why not D:** The sprint review is a collaborative working session, not a one-way status report to the sponsor. Treating it as status reporting misses its purpose of gathering stakeholder feedback to adapt the product backlog.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).