CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 43 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: When the sprint goal becomes obsolete due to a significant change in business context
Explanation
Sprint cancellation is rare and should happen only when the sprint goal becomes obsolete — for example, if the business context changed dramatically (company pivots, technology becomes unavailable, major external event) making the sprint's goal no longer relevant. Not completing all sprint items is normal and does not warrant cancellation — incomplete items return to the backlog. Product owner dissatisfaction alone is not sufficient reason to cancel.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free