CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 43 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: When the sprint goal becomes obsolete due to a significant change in business context
Explanation
Sprint cancellation is rare and should happen only when the sprint goal becomes obsolete — for example, if the business context changed dramatically (company pivots, technology becomes unavailable, major external event) making the sprint's goal no longer relevant. Not completing all sprint items is normal and does not warrant cancellation — incomplete items return to the backlog. Product owner dissatisfaction alone is not sufficient reason to cancel.
**Why not B:** Not completing every sprint backlog item is a normal occurrence in agile delivery. Incomplete items return to the product backlog to be reprioritized; the sprint goal can often still be met, so this does not warrant cancellation.
**Why not C:** Although the product owner is the one with authority to cancel a sprint, that authority is reserved for when the sprint goal becomes obsolete — not for redirecting the team at will. New priorities belong in the product backlog and are addressed in the next sprint planning.
**Why not D:** Dissatisfaction with the team's progress should be addressed through transparency, the sprint review, and the retrospective, not by cancelling the sprint. Cancelling for this reason undermines the team's focus and the stability the time-box provides.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free