CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 52 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A product owner de-prioritizes a planned feature after user testing reveals it is not valued, and adds a new feature users requested
Explanation
Responding to change means incorporating new information — in this case, user testing revealing that a planned feature is not valued. The product owner responds by re-prioritizing the backlog: removing or deferring the undervalued feature and adding the feature users actually want. This is adaptive response in action: empirical learning driving plan adjustment.
**Why not A:** Rejecting a stakeholder change request to protect the schedule baseline puts following the plan ahead of responding to change. It treats the original plan as something to defend rather than something to adapt as new information emerges — the opposite of this agile value.
**Why not B:** Completing all planned sprint backlog items exactly as estimated shows accurate planning and execution, but no new information or change is involved. Nothing in this example shows the team adapting its plan in response to learning.
**Why not D:** Following the original plan without any changes for 12 months is the clearest example of following a plan rather than responding to change. Over that period new information almost certainly emerged, and ignoring it is exactly the behavior this agile value cautions against.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).