CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 51 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Investigate whether story estimates are consistently low, backlog items are not properly refined, or team capacity is overcommitted during sprint planning
Explanation
Consistently failing to complete sprint backlog items signals a planning calibration problem, not necessarily a time problem. Root causes to investigate: Are estimates consistently optimistic? Are stories large and unrefined when brought into sprint planning? Is the team accounting for meetings, learning, and overhead in capacity planning? Extending the sprint without understanding the root cause may just create longer periods of the same problem.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).