CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 51 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Investigate whether story estimates are consistently low, backlog items are not properly refined, or team capacity is overcommitted during sprint planning
Explanation
Consistently failing to complete sprint backlog items signals a planning calibration problem, not necessarily a time problem. Root causes to investigate: Are estimates consistently optimistic? Are stories large and unrefined when brought into sprint planning? Is the team accounting for meetings, learning, and overhead in capacity planning? Extending the sprint without understanding the root cause may just create longer periods of the same problem.
**Why not A:** Hiring additional team members does not address the root cause of the planning problem. If estimates are optimistic or stories are unrefined, a larger team will still overcommit, and adding new members typically lowers velocity temporarily while they onboard and the team re-forms.
**Why not B:** Extending the sprint to 4 weeks treats the symptom rather than the cause. Without fixing estimation, refinement, or capacity planning, the team is likely to overcommit for the longer sprint as well, and longer sprints delay feedback and reduce opportunities to inspect and adapt.
**Why not C:** In Scrum, the Scrum Master does not assign work; developers self-organize and pull work from the sprint backlog. Redistributing assignments also does not address whether the team is committing to more work than it can complete.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).