CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 53 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 10 sprints — assuming velocity remains constant and no new items are added to the backlog
Explanation
350 story points ÷ 35 story points/sprint = 10 sprints forecast. This estimate assumes: current velocity remains constant (no increase or decrease); no significant new items are added; and no significant changes in team composition. These are important caveats — backlog velocity forecasts give a planning estimate that should be revisited as the project progresses.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free