CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 53 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team's velocity is 35 story points per sprint (2-week sprints). Their product backlog contains 350 story points. How many sprints will the project likely take, and what does this forecasting assume?
Show answer & explanation

Correct answer: 10 sprints — assuming velocity remains constant and no new items are added to the backlog

Explanation

350 story points ÷ 35 story points/sprint = 10 sprints forecast. This estimate assumes: current velocity remains constant (no increase or decrease); no significant new items are added; and no significant changes in team composition. These are important caveats — backlog velocity forecasts give a planning estimate that should be revisited as the project progresses.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).