CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 13 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Yes — the high uncertainty, evolving stakeholder positions, and need to learn from early proposals' reception all favor an adaptive, iterative approach to policy development
Explanation
Policy development with uncertain outcomes, evolving stakeholder positions, and the need to learn from initial proposals' reception shares many characteristics with adaptive project work: high uncertainty, the right answer emerges through iteration, frequent feedback is essential. Adaptive thinking — piloting a policy, studying its reception, refining the next version — is a valid approach even in government contexts. The specific agile framework (Scrum vs. Kanban vs. custom iterative approach) may differ from commercial software development.
**Why not A:** Adaptive approaches are not limited to software development. Any work characterized by high uncertainty, evolving requirements, and a need for frequent feedback can benefit from iterative delivery — including policy development, where the right outcome emerges from how early proposals are received.
**Why not B:** Government work does carry procedural and governance requirements, but these do not make adaptive approaches incompatible. Iterative cycles can operate within required governance, and the scenario's complexity, conflicting interests, and shifting political conditions make a rigid, fully upfront approach riskier, not safer.
**Why not D:** An adaptive approach is not tied to a single framework or cadence. Scrum with two-week sprints is only one option; Kanban or a custom iterative approach may suit policy work better. The value comes from iteration and feedback, not from adopting a specific framework.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).