CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 12 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The team reviews completed work at the end of each iteration and adjusts the approach for the next iteration based on findings
Explanation
'Inspect and adapt' is a core adaptive principle. The team regularly inspects what they built (sprint review), how they built it (retrospective), and uses those inspections to adapt their product direction and process. This systematic cycle of inspection and adaptation at the end of each iteration is what makes adaptive approaches self-correcting.
**Why not A:** Monthly risk register reviews are a periodic monitoring activity typical of predictive approaches. Updating risk probabilities involves some review, but it is not the team inspecting completed work at the end of each iteration and adjusting its approach, which is the hallmark of inspect and adapt.
**Why not B:** Reviewing deliverables against specifications before acceptance is a quality control activity. It inspects the product but lacks the adaptation element: using the findings to adjust the team's approach for upcoming work.
**Why not C:** Reviewing and updating the project charter at project close happens once, too late to influence how the work is done. Inspect and adapt depends on frequent, regular cycles throughout the project so that learning can shape the next iteration.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).