CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 14 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

The Agile Manifesto values 'customer collaboration over contract negotiation.' In practice, this means:
Show answer & explanation

Correct answer: Ongoing customer involvement and feedback throughout development is more valuable than negotiating exact deliverables upfront

Explanation

This Agile Manifesto value emphasizes that continuous customer involvement produces better outcomes than trying to specify everything in a contract upfront. Rather than negotiating exact deliverables for fixed price, adaptive approaches favor collaborative relationships where customers and teams work together, with customers actively shaping the product through regular participation.

**Why not A:** The Manifesto states that while there is value in the items on the right, the items on the left are valued more. Contracts are still used in agile projects; they simply should not replace ongoing collaboration with the customer.

**Why not C:** Customer collaboration welcomes changing requirements, but change is never free. In adaptive approaches, new work typically displaces lower-priority backlog items or affects cost and schedule—changes are managed through prioritization, not absorbed without impact.

**Why not D:** Adaptive projects still use formal agreements with customers, often structured to support flexibility rather than fixed specifications. The value statement prioritizes collaboration over negotiation; it does not eliminate the need for agreements.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).