CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 54 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Completing usable, working increments is how progress is measured — not documentation, meetings, or % completion estimates
Explanation
This Agile Manifesto principle means that actual working functionality — not documents, not plans, not 'partially done' work — is the true measure of progress. A team that writes 50 pages of design documents has made less measurable progress than a team that delivers a working feature users can interact with. This focus on tangible deliverables provides honest, verifiable progress measurement.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).