CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 11 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

In adaptive project management, the product backlog is BEST described as:
Show answer & explanation

Correct answer: An ordered list of work items to be completed, prioritized by value and urgency

Explanation

The product backlog is an ordered (prioritized) list of all work to be done on the product — features, enhancements, bug fixes, and other items. It is continuously refined, with high-priority items at the top in detailed form and lower-priority items in less detail. The product owner is responsible for backlog management and prioritization.

**Why not A:** A list of project risks ordered by priority describes a risk register, not the product backlog. While risk-response work can appear as backlog items, the backlog covers all work to be done on the product — features, enhancements, fixes — prioritized by value.

**Why not C:** The product backlog is not a detailed long-range plan. Adaptive approaches avoid detailed planning far into the future; only the items near the top are refined in detail, and the backlog evolves continuously as priorities and understanding change.

**Why not D:** A document listing stakeholders and their requirements describes a stakeholder register or requirements documentation. The backlog is an ordered list of work items to be delivered, not a catalog of stakeholders.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).