CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 21 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Adaptive, because each piece is unique and the design evolves through client collaboration
Explanation
Custom furniture design where features are refined through client collaboration shares key adaptive characteristics: requirements emerge through the design process, client feedback drives iterations (prototype designs, material samples), and the final product cannot be fully specified upfront. An adaptive approach — showing preliminary designs, getting feedback, refining — matches this workflow naturally.
**Why not A:** While the fabrication itself may follow established processes, each piece is unique and its dimensions, materials, and features are refined during design with the client. A predictive approach assumes requirements can be fully defined upfront, which does not fit work whose design evolves through collaboration.
**Why not C:** Building a unique piece for a specific client is a temporary endeavor that creates a distinct result, which is exactly what a project is. Choosing an approach suited to evolving requirements adds real value here; custom work is not exempt from project management.
**Why not D:** Frequent status reports keep clients informed, but informing is not the same as iterating. The underlying predictive plan would still assume requirements are fixed upfront, rather than incorporating client feedback into successive design refinements.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).