CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 22 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The Scrum practitioner — adaptive approaches require rigorous discipline: defined ceremonies, clear roles, maintained backlog, time-boxed sprints, and transparent metrics
Explanation
The Scrum practitioner is correct. Effective adaptive approaches require significant discipline: consistent time-boxing (sprints end on schedule no matter what), well-maintained backlog, regular ceremonies held consistently, defined and respected team agreements, transparent velocity and burndown metrics, and rigorous definition of done. The misconception that agile means 'no process' leads to what practitioners call 'cargo cult agile' — using agile terminology without the discipline that makes it effective.
**Why not B:** Discipline is not simply a matter of team preference. Adaptive frameworks such as Scrum build discipline into the approach itself through time-boxes, defined roles, and regular inspect-and-adapt events. Teams that treat these as optional lose the transparency and feedback loops that make adaptive delivery work.
**Why not C:** Adaptive approaches are flexible about plans and scope, not informal about process. Responding to change depends on consistently held ceremonies, a maintained backlog, and a clear definition of done, so calling them informal repeats the project manager's misconception.
**Why not D:** This is the exact misconception the question describes. Embracing change does not mean minimal process. Without disciplined time-boxing, backlog management, and transparent metrics, teams slide into 'cargo cult agile' and lose the benefits of the adaptive approach.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).