CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 20 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Sprint retrospective
Explanation
The sprint retrospective is the team's process improvement meeting held at the end of each sprint. The team inspects HOW they worked (process, collaboration, tools) and identifies what to improve in the next sprint. This is distinct from the sprint review (which inspects WHAT was built) and focuses on continuous process improvement — a core adaptive principle.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free