Skip to content
CAPMEasy

CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 20 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive project completes its first iteration. The team meets to reflect on their processes and identify improvements. This meeting is called:
Show answer & explanation

Correct answer: Sprint retrospective

Explanation

The sprint retrospective is the team's process improvement meeting held at the end of each sprint. The team inspects HOW they worked (process, collaboration, tools) and identifies what to improve in the next sprint. This is distinct from the sprint review (which inspects WHAT was built) and focuses on continuous process improvement — a core adaptive principle.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free