CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 23 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

Which of the following BEST describes the Agile Manifesto value 'working software over comprehensive documentation'?
Show answer & explanation

Correct answer: Producing working, valuable deliverables takes priority over extensive documentation, though documentation still has value

Explanation

The Agile Manifesto values working software (deliverables) more highly than comprehensive documentation, but it does NOT say documentation has no value ('while there is value in the items on the right'). Adaptive projects create necessary documentation — just not excessive documentation for its own sake. The focus is on creating value through working deliverables, with documentation supporting that goal.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).