CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 8 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

The iterative nature of adaptive approaches primarily helps manage which type of project risk?
Show answer & explanation

Correct answer: Requirements risk — the risk of building the wrong product

Explanation

The greatest risk adaptive approaches address is requirements risk: building a product that doesn't meet user needs. By delivering and reviewing working increments frequently, teams get early feedback on whether they are building the right thing. This enables course correction before investing the full project budget in the wrong direction — something predictive approaches discover only at the end.

**Why not A:** Regulatory risk from non-compliance is managed through compliance requirements, governance, and audits that are typically known up front. Short iterations do not inherently reduce the chance of non-compliance; they primarily validate whether the product meets user needs.

**Why not B:** Iterative delivery can limit wasted spending, but cost overruns are primarily managed through budgeting, cost control, and funding decisions. The core benefit of iterations is frequent feedback that confirms the team is building the right product.

**Why not D:** Team member departures are addressed through cross-training, knowledge sharing, and staffing practices. The iterative cycle of delivering and reviewing increments is not designed primarily to manage resource risk.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).