CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 9 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Physical infrastructure with detailed engineering specifications that cannot change
Explanation
Physical infrastructure with fixed engineering specifications least favors adaptive approaches. Once a foundation is poured or a steel beam is installed, it cannot be 'iterated.' Adaptive approaches work best when the deliverable can be revised based on feedback. Physical construction's irreversibility and pre-defined specifications make it a poor candidate for adaptive methodology.
**Why not A:** Novel technology with an unknown implementation approach represents high technical uncertainty, which strongly favors an adaptive approach. Short iterations allow the team to experiment, learn, and adjust the approach as they discover what works.
**Why not C:** Requirements that emerge through collaboration are a hallmark of adaptive approaches. Frequent customer feedback and incremental delivery let the team refine requirements as understanding grows, rather than fixing them up front.
**Why not D:** A startup product with uncertain market fit benefits greatly from an adaptive approach. Delivering incrementally and validating assumptions with real users allows the team to pivot quickly based on market feedback.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).