CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 7 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

A company wants to use an adaptive approach for a large enterprise software implementation. The software has been chosen (off-the-shelf ERP), most configuration is well-documented, and the timeline is fixed by contractual obligations. Is an adaptive approach appropriate?
Show answer & explanation

Correct answer: Partially — configuration of known modules could be predictive, but novel customizations might benefit from adaptive approaches

Explanation

This scenario calls for nuanced methodology selection. Known ERP configuration with documented steps suits a predictive approach. But custom development or novel integrations — where the right approach must be discovered — could benefit from adaptive methods. A hybrid approach often works best for ERP implementations: predictive for structured configuration, adaptive for discovery-heavy customizations.

**Why not A:** A fixed contractual timeline does not by itself rule out adaptive approaches. Adaptive methods often fix time and cost and flex scope through prioritization. The more important factor is whether the work is well understood or requires discovery.

**Why not B:** Size alone does not determine whether an adaptive approach fits. Large ERP implementations can be broken into increments; the deciding factor is the degree of uncertainty in the work, not the overall size of the implementation.

**Why not C:** Not all software projects benefit from agile methods. When the work is well understood and the steps are documented — as with configuring known ERP modules — a predictive approach is often more efficient. The approach should be chosen based on the nature of the work, not simply because it is software.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).