CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 44 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The 'almost done' syndrome — the value of adaptive methods comes from actually completing work and measuring it against definition of done
Explanation
'90% done' that stays at 90% for weeks is a classic project management anti-pattern. Adaptive approaches address this through: time-boxed sprints that force completion (or not), strict Definition of Done criteria, and transparency through burndown charts that show actual remaining work. Work is either done (meets all DoD criteria) or not done — partial credit creates false confidence.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free