CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 32 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

The 'definition of done' (DoD) in an adaptive project means:
Show answer & explanation

Correct answer: A shared team agreement defining what criteria must be met for an increment to be considered complete

Explanation

The Definition of Done (DoD) is a team agreement that specifies all criteria that must be met before a work item or sprint increment can be called 'done.' It might include: code written, unit tested, code reviewed, integration tested, documented, and meeting quality standards. A clear DoD creates shared understanding, prevents misalignment, and ensures quality consistency across team members.

**Why not A:** Activities that must be completed before a sprint begins relate to readiness (sometimes called a 'definition of ready'), not to when work is considered complete. The DoD applies to finished work items and increments, not to sprint preconditions.

**Why not C:** The DoD is not owned solely by the product owner, and it is not applied only once at project completion. It is a shared team standard applied to every increment throughout the project.

**Why not D:** Acceptance criteria agreed at contract signing are fixed, project-level terms set with the customer. The DoD is a team-defined quality standard that applies to every increment and can evolve as the team matures.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).