CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 58 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

What is 'backlog refinement' (also called backlog grooming) in Scrum?
Show answer & explanation

Correct answer: The ongoing activity of reviewing, detailing, estimating, and prioritizing backlog items to prepare them for upcoming sprints

Explanation

Backlog refinement is an ongoing activity (not a formal ceremony) where the team and product owner review backlog items: clarifying requirements, breaking large items into smaller ones, estimating story points, and ensuring high-priority items are detailed enough for upcoming sprint planning. Well-refined backlog items make sprint planning more efficient and reduce mid-sprint clarification needs.

**Why not A:** The sprint review is a separate Scrum event where stakeholders inspect the completed increment at the end of a sprint. Backlog refinement looks forward, preparing upcoming items rather than evaluating finished work.

**Why not C:** Removing completed items is not the purpose of refinement. Refinement focuses on items still to be done: clarifying, splitting, estimating, and ordering them so they are ready for future sprints.

**Why not D:** Breaking user stories into technical tasks is typically done by the developers during sprint planning when they build the sprint backlog. Refinement is broader, covering clarification, sizing, and prioritization of product backlog items.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).