CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 59 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Explain that adaptive approaches are compatible with fixed delivery dates — the date is fixed, but scope is managed adaptively to maximize value delivered by that date
Explanation
Fixed delivery dates are fully compatible with adaptive approaches. In fact, adaptive methods handle fixed dates better than predictive: when the date is fixed and scope may not be fully deliverable, adaptive prioritization ensures the highest-value items are delivered first. If time runs short, lower-priority items are deferred — not the entire product. The team commits to the date; the product owner prioritizes to maximize value within it.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).