CAPM Practice: Explain when it is appropriate to use an adaptive approach

Question 59 of 61 in Explain when it is appropriate to use an adaptive approach

Pick an answer below — you'll get the explanation instantly, no signup.

A team member says 'We can't use agile because our client requires a fixed delivery date.' What is the BEST response?
Show answer & explanation

Correct answer: Explain that adaptive approaches are compatible with fixed delivery dates — the date is fixed, but scope is managed adaptively to maximize value delivered by that date

Explanation

Fixed delivery dates are fully compatible with adaptive approaches. In fact, adaptive methods handle fixed dates better than predictive: when the date is fixed and scope may not be fully deliverable, adaptive prioritization ensures the highest-value items are delivered first. If time runs short, lower-priority items are deferred — not the entire product. The team commits to the date; the product owner prioritizes to maximize value within it.

**Why not A:** Telling the client that fixed dates are incompatible with agile is simply inaccurate. Adaptive approaches routinely operate within fixed dates by managing scope rather than time. This response misinforms the client and needlessly undermines confidence in the approach.

**Why not B:** Using an agile approach in secret while reporting predictively to the client is deceptive and violates the honesty and transparency expected of project practitioners. It also removes the client from the collaboration and feedback that make adaptive approaches effective.

**Why not C:** Agreeing and switching to a predictive approach accepts a false premise. A fixed delivery date alone is not a reason to abandon an adaptive approach. Tailoring decisions should be based on the actual characteristics of the project, not on a misunderstanding of how adaptive methods handle time constraints.

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).