CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 57 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Use a fixed price for a defined scope of early iterations or an initial release, with adaptive flexibility for subsequent phases — or use a time-and-materials contract with a budget cap
Explanation
Fixed price and adaptive approaches can coexist with thoughtful contract structuring. Options include: Fixed price for a defined MVP or first release (well-defined scope, adaptive delivery); time-and-materials with a not-to-exceed cap (controls budget, allows adaptive scope); fixed price per sprint (each sprint has fixed cost, scope varies). The key is aligning the contract structure with adaptive value delivery while managing the customer's need for budget certainty.
**Why not A:** Switching to a predictive approach just to fit the contract type lets the contract dictate the delivery approach rather than the nature of the work. Because fixed price and adaptive delivery can coexist through thoughtful contract structuring, abandoning adaptive methods sacrifices their benefits unnecessarily.
**Why not C:** Refusing to work under a fixed price contract is unnecessarily rigid and ignores the customer's legitimate need for budget certainty. A fixed price is not inherently incompatible with adaptive methods when it is applied to a defined MVP, an initial release, or individual sprints.
**Why not D:** Freezing all requirements at contract signing removes the adaptive flexibility that makes the approach valuable, effectively turning the project into a predictive one. It locks in requirements before the team and customer have learned enough to know what delivers the most value.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).