Question 24 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

In adaptive planning, who creates user stories?
Show answer & explanation

Correct answer: Collaboratively by the product owner, developers, and other stakeholders based on user needs

Explanation

User stories are most effective when created collaboratively. The product owner contributes business knowledge and user needs; developers contribute technical perspective on feasibility and complexity; other stakeholders (users, UX designers) contribute real user insights. This collaboration produces stories that are both valuable and feasible, with shared understanding that reduces misalignment during implementation.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).