CAPM Practice: Explain the components of an adaptive plan
Question 23 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: When significant new information emerges that changes the team's understanding of the story's complexity or approach
Explanation
Re-estimation is appropriate when new information materially changes the team's understanding: technical discovery changes the implementation approach; dependencies are identified; the story scope is clarified or expanded. Automatic re-estimation of all backlog items every sprint wastes time. Targeted re-estimation, triggered by new information, keeps estimates useful without excessive overhead.
**Why not B:** The development team owns estimates, not the product owner. The team should proactively re-estimate when they discover significant new information, without waiting for explicit PO direction; deferring entirely to the PO contradicts team ownership of the technical work.
**Why not C:** Retrospectives focus on improving team processes and collaboration, not on backlog refinement or re-estimation. Re-estimating every backlog item every sprint creates excessive overhead for stories that have not changed and provides no accuracy benefit.
**Why not D:** Estimates in agile are informed guesses that improve as understanding grows. Refusing to update estimates when material new information emerges leads to inaccurate forecasts, poor sprint planning, and a false sense of certainty — adaptive estimation is a core agile principle.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).