CAPM Practice: Explain the components of an adaptive plan
Question 25 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: No — organizational governance documents (business cases, charters, executive reports) can coexist with adaptive team-level practices; the key is adapting the format and timing of governance documents, not eliminating them
Explanation
Organizational governance (business cases, charters, budget approvals, executive reporting) serves governance purposes that remain important regardless of team-level methodology. Adaptive teams can produce the required governance documentation at appropriate intervals while working adaptively within sprints. The governance framework and the development methodology operate at different levels. The goal is adapting governance documentation to be more concise and timely, not eliminating it.
**Why not A:** Sprint plans and product backlogs are team-level artifacts. They do not replace the business cases, charters, and executive reporting that organizational governance relies on, so abandoning those documents is not necessary.
**Why not B:** Keeping all traditional documents without change ignores the need to adapt their format and timing to adaptive delivery. Governance documentation should become more concise and timely, not stay exactly as it was.
**Why not C:** Replacing all traditional documents with agile artifacts confuses the governance level with the team level. Governance documents serve organizational purposes that remain important regardless of team-level methodology.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).