CAPM Practice: Explain the components of an adaptive plan
Question 12 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Design the release plan with releases timed to coincide with approval cycles, ensuring regulatory deliverables are produced as potentially shippable increments that can be submitted for approval
Explanation
External approval cycles can be accommodated in adaptive planning by treating regulatory submissions as releases. The team plans sprints so that approval-required deliverables are potentially shippable (meeting regulatory standards) at the approval cycle date. Between approvals, the team continues adaptive development. This requires coordination between adaptive development practices and regulatory submission requirements, but the approaches are compatible.
**Why not B:** Adaptive approaches can accommodate external approval gates. Fixed external dates can be treated as release milestones, with iterations planned so that the required deliverables are ready when each approval cycle arrives.
**Why not C:** Pausing all sprints to compile documentation treats compliance as a separate end-of-cycle activity. Regulatory documentation should be built incrementally as part of each sprint's definition of done, so deliverables are always ready for submission without halting development.
**Why not D:** Switching methodologies back and forth around each approval period adds unnecessary disruption and overhead. The approval gates can be handled within adaptive planning by aligning releases to the approval cycles, without abandoning the adaptive approach.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).