Skip to content
CAPMMedium

CAPM Practice: Explain the components of an adaptive plan

Question 11 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

A team is planning their third sprint. They complete sprint planning in 30 minutes for a 2-week sprint. This could indicate:
Show answer & explanation

Correct answer: The backlog items may be insufficiently refined or the team is not thoroughly discussing the sprint's approach, risking mid-sprint surprises

Explanation

30 minutes for a 2-week sprint is too short (Scrum Guide suggests up to 4 hours). Rushed sprint planning typically signals: stories are not well refined (detail that should have been established in refinement will surface mid-sprint), the team is not deeply discussing approach and dependencies, or participation is superficial. This often leads to mid-sprint clarification needs that disrupt flow and cause incomplete deliveries.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free