CAPM Practice: Explain the components of an adaptive plan
Question 11 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The backlog items may be insufficiently refined or the team is not thoroughly discussing the sprint's approach, risking mid-sprint surprises
Explanation
30 minutes for a 2-week sprint is too short (Scrum Guide suggests up to 4 hours). Rushed sprint planning typically signals: stories are not well refined (detail that should have been established in refinement will surface mid-sprint), the team is not deeply discussing approach and dependencies, or participation is superficial. This often leads to mid-sprint clarification needs that disrupt flow and cause incomplete deliveries.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).