CAPM Practice: Explain the components of an adaptive plan
Question 13 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Planning enough to enable effective work without over-planning details that will change before they are needed
Explanation
'Just enough planning' is about planning appropriately for the time horizon. Detailed plans for near-term work (next sprint) are valuable. Detailed plans for work 6 months away are often wasted because conditions change. Adaptive planning invests planning effort where it will provide the most value, avoiding the sunk cost of detailed plans for uncertain future work.
**Why not A:** 'Just enough' does not mean the absolute minimum. Planning too little to avoid overhead leaves the team without the shared understanding it needs to work effectively, leading to confusion and rework. The goal is the appropriate amount of planning, not the least possible.
**Why not B:** 'Just enough planning' is not defined by a fixed number of hours. The right amount of planning depends on the work, the team, and the time horizon; it is about the appropriate level of detail, not a specific duration for planning activities.
**Why not D:** Adaptive planning does not ignore future sprints. Teams still maintain a roadmap, release plan, and prioritized backlog for future work, just at a lower level of detail. Planning only the immediate sprint with no thought about the future would leave the team without direction toward longer-term goals.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).