CAPM Practice: Explain the components of an adaptive plan
Question 10 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A working, tested, and documented increment that meets the Definition of Done and could be released if the product owner decides to
Explanation
A potentially shippable increment meets the Definition of Done completely — it has been developed, tested, integrated, and documented to production quality. 'Potentially shippable' means the product owner COULD release it without additional work. Whether to actually release is a business decision; the technical requirement is that it could be released. This ensures each sprint produces demonstrable, production-quality value.
**Why not A:** A prototype that demonstrates planned features is not a potentially shippable increment. Prototypes are typically incomplete or throwaway representations used to gather feedback, whereas a potentially shippable increment is production-quality work that meets the Definition of Done and could be released without additional work.
**Why not B:** Work that still needs more testing does not meet the Definition of Done and therefore is not potentially shippable. By definition, a potentially shippable increment requires no additional work before release; partially completed work is not part of the increment.
**Why not C:** The increment includes only items that meet the Definition of Done, not every planned sprint backlog item regardless of status. Incomplete items are not counted as part of the increment and are returned to the product backlog for re-prioritization.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).