CAPM Practice: Explain the components of an adaptive plan
Question 53 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Items with dependencies on other incomplete items must be sequenced after their predecessors, affecting iteration order and requiring early identification
Explanation
Dependency mapping reveals which stories must precede others. In adaptive planning, understanding dependencies helps sequence iterations logically — enabling stories are planned before dependent stories — and helps identify cross-team risks early.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).