CAPM Practice: Explain the components of an adaptive plan
Question 52 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Constraints (budget, timeline, quality standards) and the iteration goal, within which the team decides how to work
Explanation
Adaptive plans define boundaries (what must be achieved, constraints) but leave 'how' to the team. Iteration goals, budget constraints, and quality standards set direction while empowering team self-organization within those boundaries.
**Why not A:** Detailed architecture specifications prescribe the 'how', limiting self-organization.
**Why not B:** Daily task assignments from the project manager replace self-organization with command-and-control.
**Why not D:** Individual performance goals target individuals, not the team's working boundaries.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).