CAPM Practice: Explain the components of an adaptive plan
Question 54 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A time-boxed research or exploration activity to reduce uncertainty before estimating or committing to a user story
Explanation
A spike is a time-boxed investigation (e.g., 'Can we integrate with this API?') used to gather information needed to estimate or plan. Spikes reduce the risk of committing to uncertain work without sufficient understanding.
**Why not A:** A spike is not a chart notation. Scope changes may show up as jumps in remaining work on a burndown chart, but that is not what the term 'spike' means in adaptive planning.
**Why not C:** A sudden increase in velocity is a fluctuation in team throughput, not a planned activity. A spike is deliberately scheduled, time-boxed work intended to reduce uncertainty.
**Why not D:** Spikes have nothing to do with penalties. A spike is a planning and research technique, not a disciplinary measure for missed sessions.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).