CAPM Practice: Explain the components of an adaptive plan
Question 14 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: High-level themes and feature groups with approximate timelines and release milestones, acknowledging forecast uncertainty beyond 3 months
Explanation
A 12-month roadmap should be structured to match confidence levels: near-term (3 months) can be somewhat specific; medium-term (3-6 months) shows themes and major features with approximate timing; long-term (6-12 months) shows strategic direction with high uncertainty. Communicating the uncertainty explicitly — rather than hiding it in false precision — builds stakeholder trust and prevents disappointment when plans evolve.
**Why not B:** Committing to specific features on specific dates for the full 12 months creates false precision. Long-range forecasts carry high uncertainty, and fixed commitments set expectations that will likely be broken as priorities and learning evolve, eroding stakeholder trust.
**Why not C:** Limiting the roadmap to the next 3 months withholds the strategic direction stakeholders need for their own planning. Later horizons are uncertain, not unknowable — they can be shown as themes with approximate timing while the uncertainty is communicated explicitly.
**Why not D:** Listing exact user stories for every sprint over 12 months is detailed upfront planning that contradicts progressive elaboration. Backlog items are refined just in time as the team learns, so story-level plans a year out would quickly become obsolete and waste effort.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free