CAPM Practice: Explain the components of an adaptive plan

Question 15 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

What is the 'sprint backlog' composed of?
Show answer & explanation

Correct answer: The product backlog items selected for the sprint plus the team's plan for delivering them

Explanation

The sprint backlog has two components: (1) the product backlog items (user stories, features) the team selected for the sprint during sprint planning; and (2) the team's plan — the tasks and work breakdown they identified for how to complete each item. The sprint backlog is a living document, updated daily as the team learns more during the sprint.

**Why not A:** The entire product backlog is the ordered list of all known work for the product. The sprint backlog contains only the subset of items selected for the current sprint, plus the team's plan for delivering them.

**Why not B:** Items that were not completed or not accepted in a previous sprint return to the product backlog for the product owner to reprioritize. They do not define what the sprint backlog is composed of.

**Why not D:** The sprint backlog belongs to the whole team and includes the selected backlog items, not just individually assigned tasks. Agile teams self-organize and pull work as capacity allows rather than having all tasks pre-assigned to individuals.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).