CAPM Practice: Explain the components of an adaptive plan

Question 26 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

Which document in an adaptive project serves as the equivalent of a traditional project charter?
Show answer & explanation

Correct answer: Product vision or project vision statement

Explanation

Adaptive projects typically use a product vision or project vision statement to communicate the overall purpose and direction, similar to how a project charter defines scope and authorization in predictive projects.

**Why not B:** A Gantt baseline is a predictive schedule tool, not a charter.

**Why not C:** A detailed upfront specification defines requirements, not purpose and direction.

**Why not D:** A resource matrix assigns people; it does not convey purpose.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).