CAPM Practice: Explain the components of an adaptive plan
Question 48 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: It is designed to change in response to new information and feedback throughout the project
Explanation
An adaptive plan embraces change as a feature, not a flaw. It is intentionally designed to evolve — with mechanisms (backlog, retrospectives, reviews) built in for continuous planning and replanning based on real learning.
**Why not A:** Who creates the plan does not determine whether it is adaptive. Traditional waterfall plans can also involve team participation, and some adaptive plans are shaped significantly by the project manager or Scrum Master. The defining quality of an adaptive plan is its structural ability to incorporate change, not its authorship.
**Why not B:** The medium used to document or display a plan—digital versus paper—has no bearing on whether the plan is adaptive. A digital Gantt chart is still a traditional plan; a sticky-note Kanban board is adaptive. Equating technology adoption with adaptive methodology conflates tools with underlying planning philosophy.
**Why not D:** Including more risk contingencies is a feature of robust risk management in any project approach, predictive or adaptive. Traditional plans often have extensive contingency reserves and risk response plans. Having more contingencies does not make a plan adaptive; what makes it adaptive is the intentional design for iterative replanning based on emergent information and stakeholder feedback.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).