Skip to content
CAPMMedium

CAPM Practice: Explain the components of an adaptive plan

Question 49 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

How does the team's 'Definition of Done' contribute to adaptive project planning?
Show answer & explanation

Correct answer: It ensures a consistent standard for completeness, making velocity measurements meaningful and planning more reliable

Explanation

A consistent Definition of Done makes story point estimates and velocity meaningful — since 'done' means the same thing every iteration. This consistency is essential for reliable velocity-based planning.

**Why not A:** The Definition of Done is a shared checklist of quality criteria every increment must meet, not a threshold for an acceptable number of defects per release.

**Why not B:** The Definition of Done applies to individual backlog items and increments, not to project closure. Closing a project is governed by separate closure criteria and processes.

**Why not D:** The Definition of Done is not a status tracker for individual team members' assignments. It describes when work items are complete, and it applies equally to all work the team delivers.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free