CAPM Practice: Explain the components of an adaptive plan

Question 47 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

In a large program using SAFe, what planning artifact replaces the individual team release plan?
Show answer & explanation

Correct answer: Program Increment (PI) Plan with team iteration objectives and cross-team dependencies

Explanation

SAFe Program Increment Planning produces a PI Plan that aligns multiple teams on a shared set of objectives for the PI (8-12 weeks). It includes team-level iteration plans and a cross-team dependency board, replacing individual release plans.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).